WP1 – Requirement Elicitation and Community Building
Leader: iMinds, Start month: 1, End month: 36
Objectives: Gather KPI’s from companies, Engage with companies and get the association running by the end of the project.

WP2 – Benchmarking Platform
Leader: INFAI, Start month: 1, End month: 36
Objectives: Main aim is to development of the architecture upon which the benchmarks will be based. In particular, we will implement interfaces for data generators, task generators and evaluation measures.

WP3 – Benchmarks I: Generation and Acquisition
Leader: INFAI, Start month: 7, End month: 30
Objectives: The purpose of this WP is to provide benchmarks for the generation and acquisition of data.

WP4 – Benchmarks II: Analysis and Processing
Leader: FORTH, Start month: 7, End month: 30
Objectives: The purpose of this WP is to provide benchmarks for the linking and analysis of data KPI’s of the big data value chain.

WP5 – Benchmarks III: Storage and Curation
Leader: OL, Start month: 7, End month: 30
Objectives: This WP is focusing on the benchmarks related to storage and curation systems.

WP6 – Benchmarks IV: Visualization and Services
Leader: IAIS, Start month: 7, End month: 30
Objectives: The aim of this WP is to provide benchmarks for the visualisation and service part of the big data value chain.

WP7 – Evaluation Campaigns
Leader: NCSR, Start month: 1, End month: 34
Objectives: Purpose of this WP is organise benchmarking campaigns for each of the benchmarks.

WP8 – Dissemination
Leader: FORTH, Start month: 1, End month: 36
Objectives: Primary goal is to exploit and disseminate the HOBBIT results. Build a community in order to have a sustainability of the project after the official project end.

WP9 – Project Management
Leader: INFAI, Start month: 1, End month: 36
Objectives: Ensure project results, monitor progress and quality and run the administrative tasks. Optimise collaboration among the partners.